Civil Code 8000-9566 | Preliminary Notices | Stop Payment | Payment Bonds | Lien Foreclosure
The California mechanics lien statute provides comprehensive remedies for construction professionals:
| Code Section | What It Covers |
|---|---|
| Civil Code 8000-8118 | General provisions, definitions, and notice requirements |
| Civil Code 8200-8216 | Preliminary 20-day notice requirements |
| Civil Code 8400-8494 | Mechanics lien recording, enforcement, and release |
| Civil Code 8500-8538 | Stop payment notices for private works |
| Civil Code 8600-8614 | Payment bond claims for private works |
| Civil Code 9000-9566 | Public works - stop payment notices and payment bonds |
California law grants lien rights to anyone who contributes to the improvement of real property:
Most claimants must serve a preliminary 20-day notice to preserve lien rights:
| Who Must Serve | When to Serve | To Whom |
|---|---|---|
| Subcontractors | Within 20 days of first furnishing labor/materials | Owner, direct contractor, construction lender |
| Material Suppliers | Within 20 days of first furnishing materials | Owner, direct contractor, construction lender |
| Laborers (not employed by direct contractor) | Within 20 days of first providing labor | Owner, direct contractor, construction lender |
| Equipment Lessors | Within 20 days of first providing equipment | Owner, direct contractor, construction lender |
| Direct Contractors | NOT REQUIRED | N/A |
Strict deadlines apply to recording mechanics liens:
| Scenario | Recording Deadline | Legal Authority |
|---|---|---|
| No Notice of Completion or Cessation recorded | 90 days after completion of the work of improvement | Civil Code 8412(a) |
| Notice of Completion recorded (Direct Contractor) | 60 days after Notice of Completion is recorded | Civil Code 8412(b) |
| Notice of Completion recorded (Subcontractor/Supplier) | 30 days after Notice of Completion is recorded | Civil Code 8412(b) |
| Notice of Cessation recorded | 30 days after Notice of Cessation is recorded | Civil Code 8412(c) |
A stop payment notice is a powerful remedy for claimants when a construction lender is involved:
When the direct contractor has a payment bond, claimants can pursue the surety:
California law requires execution of lien releases in exchange for payment:
| Type of Release | When Used | Effect |
|---|---|---|
| Conditional Waiver - Progress Payment | When receiving progress payment, before check clears | Release is effective only when payment is actually received |
| Unconditional Waiver - Progress Payment | After progress payment check has cleared | Immediately releases lien rights for amount stated |
| Conditional Waiver - Final Payment | When receiving final payment, before check clears | Conditional release of all lien rights upon payment |
| Unconditional Waiver - Final Payment | After final payment check has cleared | Complete release of all lien rights |
Property owners often respond to lien claims with counterclaims for defective work:
| Type of Dispute | How to Address |
|---|---|
| Alleged defective work | Demand specific written description; offer opportunity to inspect and cure |
| Work not completed | Document completion with photos, punch list sign-offs, certificates of occupancy |
| Unauthorized change orders | Provide signed change orders, emails, or other written authorization |
| Scope disputes | Reference original contract, specifications, and approved changes |
| Delay claims | Document cause of delays, weather records, change order impacts |
Before writing a demand letter, confirm you have preserved your mechanics lien rights:
| Document Type | Purpose |
|---|---|
| Contract and Change Orders | Establishes agreed price and scope of work |
| Preliminary 20-Day Notice | Proves preservation of lien rights |
| Invoices and Pay Applications | Shows amounts billed and due dates |
| Payment Records | Proves amounts paid and outstanding balance |
| Daily Logs and Photos | Documents work performed and completion |
| Correspondence | Shows communication history and payment demands |
| Lien Releases Given | Shows amounts already released from lien |
Different situations call for different types of demand letters:
| Situation | Strategy |
|---|---|
| Payment overdue, lien deadline approaching | Pre-lien demand with specific deadline before recording |
| Construction lender involved | Stop payment notice demand to freeze loan proceeds |
| Lien already recorded | Lien enforcement demand with foreclosure deadline |
| Payment bond available | Payment bond claim demand to surety |
| Initial non-payment | Standard demand letter referencing lien rights |
In construction disputes, you may need to send demands to multiple parties:
Recording Requirements (Civil Code 8416):
Contents of Mechanics Lien (Civil Code 8416):
To enforce a mechanics lien, you must file a foreclosure lawsuit:
| Requirement | Details |
|---|---|
| Filing Deadline | Must file within 90 days of recording the lien |
| Lis Pendens | Must record Notice of Pending Action at time of filing |
| Court | Superior Court of the county where property is located |
| What You Can Recover | Principal, interest, attorney fees (if contract provides), court costs |
| Outcome | Judgment and potential forced sale of property |
If you served a stop payment notice on a construction lender:
Payment Bond Claim Process:
In addition to lien remedies, you can sue for breach of contract:
For public construction projects (no lien rights against public property):
| Remedy | Description |
|---|---|
| Payment Bond Claim | Public works require payment bonds; claim against surety |
| Stop Payment Notice | Serve on public entity to withhold funds from contractor |
| Preliminary Notice | Required within 20 days of first furnishing work |
| Claim Deadline | Within 30 days of completion or notice of completion |
| Lawsuit Deadline | Within 6 months of completion |
Priority Rules:
Owners commonly raise these defenses and counterclaims:
I help contractors, subcontractors, and material suppliers protect their payment rights under California mechanics lien law. From preliminary notices to lien foreclosure, I provide experienced guidance to ensure you get paid for your work.
Book a call to discuss your mechanics lien case. I will review your situation, calculate your deadlines, and recommend the best strategy to protect your payment rights.
Email: owner@terms.law
Mechanics lien deadlines are strict and unforgiving. Whether you need to record a lien, serve a stop payment notice, or foreclose on an existing lien, experienced legal guidance can help ensure you get paid for your work.
Schedule a ConsultationCalifornia Civil Code Sections 8000-9566 provide contractors, subcontractors, and material suppliers with powerful remedies to secure payment for construction work. A mechanics lien creates a security interest in the improved property, allowing you to force a sale if payment is not made. Understanding these laws and their strict deadlines is essential for anyone in the construction industry.